Most national fixture programs are already hybrid. The gondolas, wire shelving and standard wall systems come from a high-volume plant, often offshore, and the counters, feature walls and anything site-specific come from a local millwork shop. Programs run into trouble when the split is not planned: custom pieces get ordered offshore and arrive late or wrong, or standard items get built locally at a price the budget cannot carry. This guide sets out how to split a program between the two, and how to manage the seam between them.
Offshore production suits items that are identical across every store, needed in quantity, simple to pack and unlikely to change once approved:
The economics work when the order is large enough to fill containers, the design is frozen before production starts, and the opening dates are far enough out to absorb ocean freight and customs clearance. If any of those three conditions fails, the saving disappears.
Local production suits everything that is different from store to store, carries risk, or is on the critical path for opening:
The split itself is the easy part. The problems happen where the two sources meet. Five things to settle before either order is placed:
Offshore production runs on a long, fixed timeline: production, ocean freight, customs, inland freight. Local production runs on a shorter timeline that can flex. Plan backwards from each opening date, place the offshore order first, and use the local pieces to absorb the schedule risk. If an opening moves up, local items can usually be pulled forward; a container cannot. If an opening slips, finished local pieces can be held in the shop rather than in a store under construction.
Lead times depend on the program, so treat any figure you are quoted as a starting point and confirm it against the current freight and customs situation.
The unit price on an offshore quote is only part of the landed cost. A fair comparison includes:
For high-volume standard items the offshore price usually still wins after all of that. For custom and site-specific items it usually does not, which is why the hybrid approach exists.
DNS Industries builds complete fixture programs from our plant in Vaughan, Ontario, and we also work as the Canadian half of hybrid programs. In those programs we have built the custom and site-specific millwork, received and inspected offshore shipments, and staged and kitted the combined packages by store. Several multi-store brand programs have run this way through our shop. We do not make modular shelving systems ourselves, so there is no conflict in recommending where the standard items should come from.
If you are planning a rollout with an offshore supplier already in place, send us the drawings and the opening schedule and we will tell you which items we would keep local and why.
Offshore suits identical, high-volume, simple items such as gondolas, shelving and wire fixtures. Local suits cash wraps, feature walls, lit fixtures, site-specific pieces, accessibility items, first stores and replacements.
Specify laminates by manufacturer and code, and send physical control samples for paints and stains to both plants before production. Approve a first store before releasing volume.
Have the local millwork shop receive, inspect and kit them with the local pieces, so each store gets one labelled shipment and problems are found before install day.
Usually, when the volume items are large and standard. The saving comes from the standard items; trying to push custom pieces offshore tends to cost more once freight, damage, changes and delays are counted.
Related guides: Retail rollout fixture programs, Store fixture suppliers in Canada, Shipping and packaging for rollouts, Store fixture and millwork lead times.